Mayor Rhonda Hoban reminds residents that bridge elements for the Lanes Bridge construction project will be craned in this week.
Subscribe now for unlimited access.
$0/
(min cost $0)
or signup to continue reading
This means there will be significant delays to traffic anytime between the hours of 6.00am and 6.00pm up until and including Saturday, weather permitting.
“There has been a change to the duration of the delays … an amended timetable summarising the planned traffic delays is listed below and is also on Council’s website www.nambucca.nsw.gov.au.
Today, Tuesday 11 December, am: 30 minutes (min) and up to 2 hours (max).
Wednesday - Friday am and pm: 30 minutes (min) and up to 2 hours (max).
Saturday, am: 30 minutes.
Please note there will be NO pedestrian or traffic access during these closures.
Assistant General Manager, Engineering, Paul Gallagher said:
“Lanes Bridge is currently a one lane bridge under traffic light control with a 20 tonne load limit.
Work continues on construction of new Lanes Bridge:
“As previously advised appropriate signage advising of the bridge closure will be erected at the following designated intersections:
Wirrimbi Road and Rodeo Drive
Valla Road and Newee Creek Road
Giinagay Way and Ferry Street
Wilson Road and Coronation Road
Bellingen Road and Rodeo Drive
High Street and Cook Street .
“There is an alternative route to and from Bowraville via Wilsons Road and road closure information will also be provided via the MyRoadInfo and Lanes Bridge portal on Council’s website and a email alert to those who have already registered as interested parties.”
For enquiries please contact Council’s Engineering Services Department on 6568 0230 or email council@nambucca.nsw.gov.au.